What measures need to be prepared for screw conveyor operation?




screw conveyor operation.png

The operating platform, the upper and lower ladders and the protective railings should be repaired in time. During the hoisting process: it is strictly forbidden to stand under the cement silo/cement tank, and it is necessary to wait for the lifting object to be close to 1 m below the ground. Field personnel must wear a safety helmet, and operators are strictly forbidden to drink and fight on the spot.

High-altitude workers must wear seat belts. When walking, people should not look around. Do not lean against the guardrails during rest.

Before lifting: Do not place any objects on the work platform frame, adjust the center of gravity, apply the snap ring and safety hook when lifting. When installing the concrete mixing station: it should be installed once from the inside to the outside.